Safety technical measures for hoisting construction of installation works

1 All personnel participating in the construction must be familiar with the hoisting method and project content under the same output and melt quality, carry out the construction according to the scheme requirements, and strictly implement the regulations and specifications

2. During the construction process, the construction personnel must divide the work specifically and clarify their responsibilities. During the whole hoisting process, it is necessary to observe the on-site order, obey the order and obey the command, and do not leave the work post without authorization

3. During the hoisting process, there should be a unified command signal, and all personnel participating in the construction must be familiar with this signal, so that all operating posts can coordinate their actions

4. During hoisting, the whole site is allocated by the commander in chief. The sub commanders of each post should correctly execute the command of the commander in chief, so as to transmit signals quickly and accurately in July this year, and be responsible for their own responsibilities

standard requirements 5 During the whole construction process, the site shall be cleaned up and obstacles shall be removed to facilitate operation

6. During the construction, all personnel participating in the climbing operation must pass the physical examination, and fasten the safety belt in a safe position during the operation. Tools should have safety ropes, and it is not allowed to throw things down at will

7. Construction personnel must wear safety helmets. If they work in winter, they should put down their protective ears so that their hearing is not hindered

8. Live welding wires and wires should be kept away from the steel wire rope, and the distance between live lines should be kept at least 2 meters, or a protective frame should be set. When the welding wire crosses the steel wire rope, it should be separated from contact

9. When the cable wind rope crosses the highway, the height from the road surface shall not be less than 5 meters, so as not to hinder the traffic

10. Before hoisting construction, contact the local meteorological department to understand the weather conditions. Generally, it is not allowed to work in rainy and snowy days, open air or at night. If it must be carried out, anti-skid and sufficient lighting measures must be taken. At the same time, with the approval of the leader, it is strictly prohibited to hoist when the wind force is greater than force 6, and large equipment cannot be hoisted when the wind force is greater than force 5

11. If it is necessary to use structures to tie down rigging during construction, it must be checked and calculated, and can be used only after it is safe to bear and approved. At the same time, a protective layer shall be padded to ensure that structures and riggings will not be worn, but the following structures shall not be used:

(1) transmission towers and poles

(2) equipment and pipe supports in production and operation

(3) forest

(4) ground anchors that do not meet the use requirements or whose tonnage is unknown

12. Before hoisting, relevant departments should be organized to jointly conduct a comprehensive inspection according to the requirements of the construction plan, which includes:

(1) whether the configuration of construction machine rigging is consistent with the plan

(2) whether there are self inspection and mutual inspection records for concealed works

(3) whether the position of the foundation bolt of the equipment foundation (refers to the embedded bolt) meets the engineering quality requirements and is consistent with the screw hole of the equipment skirt or base

(4) whether the earthwork around the foundation is backfilled and compacted

(5) whether the construction site meets the operation requirements

(6) whether the equipment to be hoisted meets the hoisting requirements

(7) whether the construction power supply can be guaranteed

(8) understand personnel division, command system and weather conditions

(9) whether other preparations such as security, rescue, life supply, reception, etc. are implemented. After the inspection and confirmation, the lifting order can be issued. After the construction personnel enter the operation post, they must still check the post. After the inspection and confirmation, they can stand by for operation. If it is necessary to lift the next day, they should organize personnel to protect the site

13. Before hoisting, trial hoisting shall be carried out to check the stress condition of all parts of the engineering crane, and the hoisting can be continued only when the condition is normal

14. During the lifting process, without the permission of the on-site commander, it is not allowed to stay and pass under the lifting weight and near the stressed rigging

15. Generally, no one is allowed to lift or lower with the lifted object. If it is necessary to do so under special circumstances, safety measures should be taken and approved by the leader

16. The hoisting construction site should be equipped with a special area to send personnel to guard in recent years. Non construction personnel of the project are strictly forbidden to enter. Construction commanders and operators should wear marks, and they are not allowed to enter without marks; In the process of hoisting, if it is interrupted for some reason, measures must be taken to deal with it, and the heavy objects must not be suspended overnight; Once an accident occurs during the hoisting process, all operating posts should stick to their posts, strictly maintain the order on the site, and make records to analyze the causes